If you're building an ADU, junior ADU (JADU), or movable tiny house in the City of Los Angeles, there's one document that decides whether your permit moves forward or stalls: the LADBS ADU / JADU / Movable Tiny House Correction Sheet, officially numbered PC/STR/Corr.Lst.20A. Here's the part that trips up most homeowners — it isn't a form you fill out and submit. It's the checklist a city plan check engineer uses to mark up your plans and tell you what needs to change.
Understanding it before you submit is the single best way to avoid weeks of back-and-forth.
PC.STR.Corr.Lst.20A (current revision 10/01/2025) is a 14-page correction sheet issued by the Los Angeles Department of Building and Safety (LADBS), tied to the 2023 LA Building and Residential Codes. When you submit ADU plans, a plan check engineer reviews them against this list and circles every item your project doesn't yet satisfy. Each circled item cites a specific code or zoning section, so you know exactly what to fix.
Used in reverse, it's a gift: have your designer clear every item on this sheet before you submit, and you skip most correction cycles entirely.
Anyone going through standard LADBS plan check for a detached or attached ADU, a JADU, or an Ordinance Movable Tiny House. You can sidestep the architectural-correction grind by using one of LADBS's 20+ pre-approved/standard ADU plans — those bypass architectural plan check. Note this is City of LA only; the County and neighboring cities use their own lists.
The sheet checks for a complete package. At minimum:
Movable tiny house owners have extra items: DMV registration, ANSI A119.5 or NFPA 1192 certification, a screened undercarriage, utility hookups (30-amp minimum), and a notarized Owner's Declaration. JADUs require a recorded covenant (PC/STR/Aff.45) — an easy thing to forget that will hold up issuance.
One firm rule: corrections are verified only at the same office that did the original check.
The correction sheet itself is free. Fees apply to the underlying plan check and permit, calculated from your project's valuation and square footage using the LADBS fee calculator and collected in waves (submittal, resubmittal, issuance, final). Industry estimates put all-in LA ADU permit and plan-check fees around $5,000–$14,000 in 2026; ADUs 750 sf or smaller are exempt from school fees. Confirm your real numbers with the official LADBS calculator.
On timing: California law (Gov. Code 66317) requires the city to check your application for completeness within 15 business days and to approve or deny a complete, code-compliant ADU ministerially within 60 days — miss the deadline and it's deemed approved. In practice, standard plan check runs about 4–10 weeks, and each correction cycle adds 2–4 weeks. Your application expires 18 months after submittal, so don't let it stall.
Clear PC.STR.Corr.Lst.20A on the first pass and your ADU permit can move in weeks instead of months.
Sources: LADBS PC.STR.Corr.Lst.20A; LADBS Plan Review & Permitting; CA HCD ADU Fact Sheet 2026; Gov. Code 66317.